September 2022 Production Updates

Hey there, here’s our September 2022 production update.

For all news and updates, please see our Blog.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

Please note that we will be closed on Monday Sept 5, 2022 for Labour Day. We’ll be back in the office on Tuesday Sept 6, 2022.

Michael our QA engineer going through our latest batch of gantries

LongMill MK2 and Extension Kit Orders

Production continues to move fairly smoothly for all LongMill and Extension Kit orders. We have now cleared the pending queue for 48×30 and Extension kits and now lead times for all machine sizes will be more or less the same. We are expecting lead times to be around 1-2 weeks for most orders for this month.

This past month we did pause production shortly due to us running out of rail extrusions to make 48in X-axis rails, however, we have received another batch of rails that should cover for another 400-500 machines. Because we were working with our extrusion manufacturer to work out some kinks in the consistency of the rails, which placed the order on hold rather than going to press. Thankfully they were able to move the extrusions to the weekend schedule and have them made with only a few days of added delay.

X and Z gantries we also ran out as well have also been restocked. The next thing we’re expecting to run out of are the front and back steel feet for LongMill MK2 machines which we currently have 70 units worth left, however, those should be restocked back around the end of next week.

LaserBeam Orders

We are now stocked on enough LaserBeam units to last till the end of the year. Most are shipping out within a few days.

Batch 7 Production

We are now at the final third of Batch 6 Production. This means that we’re at our last 500ish machines, and we’ll be getting to the end of the batch sometime likely in December. Depending on the status of our shipments, our lead times may change around this time.

Batch 7 production has been underway for the last few months and we’ve been getting parts in to prepare. There won’t be any major changes but we’ve made some small tweaks to production overall including:

  • Small tweaks to the design of the 5mm to 8mm coupler to help customers identify which side goes on which side
  • Fully custom-produced v-wheels to improve quality control and consistency of the wheels

Some additional changes to our production reflected in Batch 6 and 7 include:

  • New tools to check the consistency of all of our rails
  • Additional checks to ensure the flatness of all gantry plates and other steel parts
  • Individual motor tuning on all control boards

When we started Batch 6 in 2021 and early 2022, we were at the height of the pandemic and supply chain constraints. Recently, we’ve seen lower lead times, shortages, and transport times than before, so we are hopeful that this new batch of machines will have a smoother production process than before.

Price increases from UPS

UPS has recently informed us that they will be charging an “Additional Handling Fee” on shipments weighing over 50lbs. Previously this limit was set to 70lbs. This means that some shipments on new orders may see roughly a $10 increase on LongMill shipping prices on new orders placed Sept 6. We are working with UPS to negotiate and reduce the impact of this charge.

August 2022 Production Updates

Hey everyone, here is the update for this month. For all news and updates, please see our Blog.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

Not too much new to report, so this will be a shorter post than usual.

LongMill 48×30 and Extension Kit Orders

We did have a stop in production last month for a short period of time as we got shorted some Y gantry plates for the 48×30 and EX plates but that has now been resolved. We’ve shipped out another batch of around 50-60 machines since.

Because of a higher than expected number of orders for the 48x30s, we are currently out of stock on X rails and are waiting for another delivery of material on August 12th. While we expected 48×30 machines to make up around 30-50% of our machine sales, we’ve now found that the larger variant has recently become nearly 60% of our sales in the last month. The new batch of rails that are on the way has been adjusted to reflect the new ratio.

Once the rails arrive, we will ship machines out again and should take about 2 weeks to complete the remaining queue.

LongMill 12×30 and 30×30 Orders

Orders for LongMill 12×30 and 30×30 have been mostly shipping out within one business day. We currently have parts in stock and ready to go.

LaserBeam Orders

We have received new drivers and are currently packing and shipping the rest of the queue. Most customers should have gotten theirs shipped already, and most new orders are going out within a week. If you have a machine on order waiting to be shipped, the Order Status page may not show as completed since both items haven’t shipped yet.

July 2022 Production Update

Hey everyone. Here’s our update for July 2022. Production continues to move along as scheduled and we are getting machines out the door as usual.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

LongMill 12×30 and 30×30 Kits

Any 12×30 and 30×30 orders have been shipping out as they come in and lead times on orders is 1-3 business days. Kits are in stock and ready to go.

LongMill 48×30 and Extension Kits

Starting last week, we have started shipping out LongMill 48×30 and the Extension Kits. At the current time of writing, we should have around 20-30 people who have received their orders or have gotten their machines shipped. If you have a pending order, you should have gotten an email from me that looks like this:

Hey there,

If you are getting this email, we’re either prepping your LongMill 48×30 or Extension Kits to ship or we’ve already shipped your order out. At the time of writing, we have 20 out the door already and another 140ish kits pending. We’re excited to start seeing LongMill 48x30s in the wild! Here’s some important info about your order.


LongMill 48×30 machines will ship in two separate boxes

If you ordered a complete 48×30 machine, your order will come in two separate boxes. In most cases, they will have one master tracking number and two child tracking numbers for each box. In some cases, we’ve had to make two separate tracking numbers for them depending on the shipping configuration. 


If you ordered any type of Extension Kit, they will come in one single box.


Timing of shipping of orders

There are a couple of new things that we’re tackling with this shipment which may affect the time you receive your orders slightly. If you’d like to check on when we’re estimating to get your order, please check our list here: https://sienci.com/order-status/


Thankfully we have all of the parts ready to ship, but there are some operational things we’re wrapping up to ensure every package has the proper documentation and paperwork done for shipping which will take some time. 


Here are a couple of general notes:


– US customers who are on military bases may take longer for us to process, as there are some technical issues with Canada Post (USPS) because some of their back-end shipping systems are not working at this time. We are working to resolve this or find alternative shipping options.


– We’re finalizing some of the packing and documentation for the extension kits. We just finished doing the final packing for the MK1 to MK2 Extension Kits with the MK2 XZ Gantry and should have the MK1 to MK2 Extension Kits with the Adapting Brackets ready in the next day or two. Our team is also finalizing the documentation which will be posted on our resources soon as well, but we will start shipping the Extension Kits tomorrow as they get packed so that they’ll be arriving in the customer’s hands by the time they are uploaded.


If you have any questions or need any other help, please feel free to reach out to us (https://sienci.com/contact-us/).


If you’re looking for a dimensioned drawing for the footprint of the machine, please feel free to download it here: https://sienci.com/wp-content/uploads/2021/12/LongMill-MK2-48×30-30×30-and-12×30-dimensions.pdf


Happy making,


Andy

New orders for 48×30 and Extension Kits will ship out in order, so we are expecting new orders to ship in about 4 weeks.

LaserBeam orders

We are waiting on another batch of LaserBeam drivers to arrive to us and should be here in about three weeks. LaserBeam orders will continue to ship when we receive the new batch.

In the meantime, please check out Scott’s latest videos on setting up the laser!

US Duties and Taxes

As a short follow-up to our last update on US Duties and Taxes. I put out a post on the Facebook group and it looks like with the exception of one customer who reached out, we’ve been able to get the LongMills cleared for everyone. We had about 15 orders get charged taxes which we’ve paid on the behalf of the customer before we sent all of the proper USMCA clearance paperwork, but we have confirmation that they have received the paperwork now so any new orders crossing into the US should get cleared properly now.

We’ve also set up an exemption on the 48×30 Extension Kits, so these orders should clear duty-free as well.

First Nations Tax Exemptions

If you are a Canadian First Nations, you may be eligible for a tax refund on completed orders. We have updated our system to process these exemptions. For more info, please visit this page.

June 2022 Production Updates Pt.2

Just another production update. For the last production update please check it out here: https://sienci.com/2022/06/01/june-2022-production-updates/

May was a tough month but it feels like things are finally turning around. Lasers are shipping again, LongMills are shipping with basically no wait time, and I’ve just gotten confirmation that the last part for the LongMill MK2 48x30s and Extension Kits will be done soon.

Just to start with something fun, here’s a little video of me riding on the CNC machine. Apparently its easier to convince people that the LongMill is super strong if we sit on it, so I’ve done this to make everyone happy.

I am running the machine at 2500mm/min on stock hardware and firmware settings.

If you want to make your own here’s some files:

Instructions:

  1. Cut out using 3/4″ material using an 1/8″ or smaller bit. If you use a larger bit, it might not fit together right because of the radius in the corners. I used MDF. The DXFs might need to be joined.
  2. Pictures of putting it together are in the ZIP file. Use a mallet to slot everything together. There is no clearance, so a lot of physical persuasion might be necessary.
  3. Bolt to the top of the X rail with M5-25 bolts and M5 T nuts
  4. Whee…

LongMill MK2 12×30 and 30×30 lead times

Lead times for new machine orders 1-3 business days. All of our parts are in stock and we are currently packing and shipping orders as they come.

It feels like a really really long time since we’ve been caught up on orders. I am happy that we were able to navigate through everything to finally get everything together. We’re also expecting another 500 Y gantries to arrive in the next few weeks, which will cover us for the next 400-500 machines. This means that overall, I think we’ll be able to keep lead times short for another 2 months.

Our next bottleneck is likely to be aluminum rails, as we still need to order another batch of them. However, because we’re limited in space right now and we still have quite a few left, we’ll likely hold off on the order until July.

It’s a relief, but at the same time, our work isn’t done yet. We’re about halfway through sourcing and production for the next batch, Batch 7 and getting it ready for the end of the year.

LaserBeams are shipping

Another batch of LaserBeams getting shipped out

Finally, the drivers are working and being shipped. We have about 100 shipped out from the queue and should have most of the rest of them done tomorrow.

We’ll have to wait a little bit for Ikenna to give us a full update, but since we only received 200 laser drivers, once we use them up, it’ll likely be a couple more weeks for us to get another batch once we are sold out. We’ll more concrete dates soon, but we will keep a 6 week lead time for new orders. In the meantime, we’re working on a ton of new resources for the laser. We also now have LightBurn for sale on our website!

LongMill MK2 48×30 and Extension Kit production

New cables for the 48×30 and Extension Kits have arrived and earlier than expected. We’ll be packing them up for the new kits as well as for our store. We’ve gotten a lot of customers asking for extension cables, and this should let folks have more flexibilty in relocating their controllers and such.

Now that these are in, all that we’re waiting on are the extension cables for the routers, which should be here in the next week, as well as the Y gantries, which will go to the coaters next week and be back here at the end of the week or sometime the following week. Thankfully all of these parts are sourced and made locally and turnaround times are a lot shorter than doing them overseas.

Our saw was broken down for about two weeks recently, but we’ve just been able to get it going again and have cut about 25 rails. We should have another 100-200 rails cut tomorrow and early next week.

Rails being tapped
Lead screws and drag chains being packed

This means that we’re really close to having all of our parts to start shipping the new kits. As I mentioned in the last update, it’s likely our biggest bottleneck will be how quickly we can have the instructions ready, but our engineers are making good progress so far.

We don’t have exact shipping dates so far and we’ll have a better estimate in the next two weeks. At least in the meantime, if you’re looking to order a 48×30, it will ship sometime in July.

June 2022 Production Updates

May has been a pretty rough month, dealing with some QA issues and other manufacturing delays. Overall, we’ve been able to keep time to ship to time to order for LongMills down to about 1-2 weeks for most customers at this current time, but we’ve faced some challenges in keeping production moving smoothly.

This is our June 2022 production update. We’ll touch on some news from May and talk about stuff to expect in June.

Visiting Andy McTaggart, one of our beta testers

Current lead times

Lead times currently are 1-2 weeks on MK 12×30 and 30×30. Our lead time is mostly affected by when our newest batch of Y gantries will arrive. We are expecting them to be ready for coating by Thursday and come back to us at the start of next week.

*UPDATE Jun 3, 2022* Our new batch of Y gantries have arrived today and have passed QA inspection! We are packing up machines now to ship and should have things continue to go out!

Our mini-saga of Y gantries

About two months ago when we first started manufacturing the new batch of 1000 Y gantries, our manufacturer jumped the gun and started producing new plates before we provided the new revision of plates. Due to this, we needed to recut another 1000 Y gantries with the new revision and keep the old version in storage for use in the future potentially. Because there were already quite a few other parts getting processed at the time, the overall time for us to get the materials down to the coating shop was unaffected.

It took another week and a half to get everything coated, but just as the finished parts were loaded up onto the truck, the pallet fell, causing many of the plates to get damaged. We received a partial order of undamaged parts (X gantries, Z gantries, front and back feet, and controller box parts), but unfortunately, all of the Y gantries were damaged and needed to be fixed.

In the meantime, we continued to fulfill orders with the remaining number of gantries we had on hand. However, at the current time of writing, we are out of Y gantries.

About a week later, we received the fixed Y gantries, but then we ran into another issue.

We had changed to a new process of drilling and tapping holes, which referenced the center bearing hole to cut some of the smaller holes on the plate. Previously, we were laser cutting all of the holes, but we switched to the CNC method to speed up the process and automate the tapping process.

Although we are investigating the incident, it we suspect that the workholding was not done correctly on this batch of parts, causing all of the holes to be slightly off from where they need to be.

Initially, we did find that 1/3rd of the plates had the holes in the correct place, but after doing further checking we found that the tapping angle of the threads was also dramatically off, and none of the plates were able to be used.

Thankfully, our manufacturer which we’ve worked with for the last 6 years has been working hard with us to rectify the issue and implement new processes to eliminate this issue in the future. We’ve also sent a few of the members from our manufacturing team to set up another tapping cart and make a new batch of gantries as quickly as possible. At the time of writing, I’ve been informed that we’ve just finished 500 Y-gantry plates and will be shipping them to be coated on Thursday.

We’re currently working with our coating manufacturer to get this batch of parts to get coated as soon as possible and are looking at sometime next week when we’ll be able to get them.

Laser driver issues

For the original post: https://sienci.com/2022/05/31/bittele-sent-1oz-boards-again-makerfab-drivers-waiting-to-be-cleared-at-the-local-center/

Of course, to add to the issues for this month, the second batch of repaired driver boards for the laser still has issues. We are waiting on another batch of drivers from another manufacturer that should be arriving this week.

48×30 MK2s and Extension Kits

We have now started packing and prepping the parts for the MK2 48×30 machines and the Extension Kits. We are waiting on the production for the wiring and Y gantries to be done over the next couple of weeks, but progress on those is moving along on time and we are still on track to ship in July.

Parts that are being processed currently include:

  • Extended X rails
  • Couplers
  • Lead screws
  • Drag chains
  • ACME locking nuts
  • Delrin nuts
  • Bearings

Parts to start packing include:

  • MK1 to T12 Delrin nut adapter
  • Wiring management parts
  • Wires
  • Y gantries

At the current time, we starting packing and processing the new kits. Once we get the wiring and Y gantries we’ll have full kits ready to go. Here are our rough estimated delivery times:

  • Y gantries: 3rd week of June
  • Wiring: 2nd week of June

Although production of these parts is coming along fairly smoothly so far, I am currently expecting the resources for the assembly to be one big hurdle to get through and may make a big impact on the timing of shipments. Of course, we don’t want to delay shipments, but we also don’t want to hand the product over to the customer without proper instructions on using it. We will put out more updates on the timing of shipments as we continue to develop the resources for the 48×30 machines.

So far, our beta testers have been using the extended version of their LongMills with lots of success. If you want to see Dana, who’s had his extension kit for testing for the last little bit, check out the video below:

Wrapping up the beta testing program

We just finished filming our last beta tester’s interview this past weekend. It’s been such a great journey to follow along with each user to see how they grow and learn to use their machines.

Our last beta tester interview will be posted in about 1 week from now.

If you want to see the interviews, please check our playlist here:

May 2022 Production Updates

Hey everyone, here’s our May 2022 production update.

Overall production continues to move along smoothly and machines are going out the door at a good pace. In a good way, we don’t have too much to report on.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

Lead times for LongMill MK2 12×30 and 30×30 orders

We’re excited to be getting through the rest of the queue on the LongMill MK2 12×30 and 30×30 orders sooner than expected. Patrik and the rest of the packing crew have now pushed out over 400 machines over the last four weeks, and are expecting to complete the rest of the queue sometime next week. This means that new orders should ship in 2-3 weeks placed today.

Incoming materials and production

Production has been moving along slowly without part shortages. Once the queue is complete, we are expecting to have enough parts to pre-pack and ship another 70 machines with the gantries and steel parts that we currently have. Another batch of these parts is expected to arrive in about 2 weeks, so we believe that we’ll be able to continue packing and shipping as orders come. After these parts arrive, we’ll have plenty of material to keep us busy for the next 2-3 months.

It’s been a while since this has happened, but we’re now at the point where our production capacity is exceeding our demand, and our goal is to get things packed up and ready to go as more folks get their machines and word on the LongMill MK2 continues to spread.

Some other general news

  • Our company is growing. We have a couple of new people joining our team in marketing, operations, and engineering! We’re also working on hiring new folks for software development and customer support.
  • The LongMill MK2 assembly video is being edited now and we are expecting it to go live in the next week or two.
  • Check out Dana’s latest video where he shows off his new MK2 and extended 48×30 MK1 machines! https://www.youtube.com/watch?v=Mi6Dqqvy-pI

April 2022 Production Update Pt.2

Hey everyone, here’s just a quick update about the production here at Sienci.

By the way, we are having a livestream on Youtube tomorrow, if you’d like to be part of it, we’ll be live at noon (EST) on Friday April 22! This livestream will cover some of the development work happening at Sienci Labs as well as a bunch of stuff about the LongMill MK2.

Shipping

We’ve been working hard to get as many machines out the door as quickly as possible. Now, at the time of writing, we’ve just about shipped 250 machines. Our support team has been reporting that issues have been fairly low and comments about the machine have been overall very positive! If you’d like to follow along on our progress, feel free to check out our page here: https://sienci.com/order-status.

We’re expecting to keep up with packing as we are currently. Please make sure to stay tuned for more updates.

Email notification issues

UPDATE: As of April 28th, we have fixed the email notification issue and tracking information is now being sent automatically as orders are completed. For more info, please see our post here: https://sienci.com/2022/04/28/completed-order-emails-and-tracking-notifications-are-back-online/

We’ve recently run into an issue (since April 18th) where shipping notifications for LongMill MK2 orders are not being sent. All other email notifications for orders (parts, bits, and other products) are being sent, and the only orders that are being impacted are the ones with LongMill MK2s. In the meantime, we are sending out the notifications manually, so please keep an eye out for them. We are continually working on fixing this issue, and if your order is showing completed on our Order Status page, please get in touch with us for the tracking info.

We suspect that there may be some bugs with the system as there was some updates that happened around this time. We’ll continue monitoring the emails being sent out so that we can keep folks updated as best as we can.

We are also experiencing some issues with auto-syncing orders with the Order Status page, so we have been updating it throughout the day. Please note that there may be a bit of delay day to day on the status of the items on the page until we fix the system.

Incoming materials

We’ve now reached the first 500 machines sold for Batch 6, which means that we are now about a third of the way through. We currently are stocking 1500 machines worth of parts, with the exception of the rails and the gantries. We initially ordered 500 sets of rails and gantries to start the batch and we’ve placed another batch of those parts to come in soon.

Materials for rails which were slated for early June arrival have been completed early and are expected to be delivered to us soon. Some will be here tomorrow and some will be here next week. This also covers the rails we need for the 48×30 machines and extension kits, which means that we’ll be starting prepping and cutting for those orders as well.

Gantry plates and feet are in production currently, and we are expecting all of them to be cut, formed, and painted at the start to middle of May. Once those parts are available, these parts will be used for machines for the next 500 units.

Initially, we were expecting to start shipping machines after the first 500 in June, but it looks like we’ll be able to chug along with production without interruptions.

LaserBeam Drivers

If you didn’t see Ikenna’s update for the LaserBeam, please make sure to read it here: https://sienci.com/2022/04/14/laserbeam-driver-delay-update/

We are currently working with Bittele and other PCB manufacturers to work on getting drivers in as soon as we can.

April 2022 Production Update

Hey everyone, here is our April 2022 production update.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

I’m happy to announce that the LongMill MK2s are now shipping! We received our container last week and have started shipping since. Here’s some customer feedback from one of the first people to pick it up:

MK2 Production

At this current time, we now have enough materials on hand to ship around 500 machines. Our team continues to pack and assemble kits as quickly as we can. At the time of writing, we’ve gotten 48 machines shipped out since last Thursday.

For general updates on where your order is on the list, please see our Order Status page. An estimated time for shipping can also be found on the page. We are aiming to average around 50 machines shipped per week. Please note that this number can vary a lot depending on staff availability and production schedules. Please also note that this is an average we are shooting for, but the number may vary day-to-day, as some days we may be able to ship more than others. Because of this, we cannot provide exact dates on when machines will ship for each order, but an email will be sent the week before your order is ready to ship to let you prepare and let you know that things are heading your way.

I’ve updated the estimated time to completion on our Order Status page to reflect our expected delivery times. Please make sure to check it out for our latest estimate on when your machine will ship.

We are expecting the first week to be a little bit slower and for things to pick up as we keep packing since some of our new packing material which was designed to improve our packing speed has not arrived yet and we are using general off-the-shelf material in the meantime. The new packing material is expected to arrive this week, but it has previously been pushed back a few times and it hasn’t been clear the exact delivery date due to cardboard shortages.

Materials

We now currently have the material needed to build the next 500ish machines, which means that we have everything we need to cover all of the machines in queue currently. We are still waiting on some additional packing material to arrive, but for the time being, we’ve substituted final production packaging with some off-the-shelf materials we were able to use in the meantime.

After the first 500 units, we’ll be waiting on another batch of gantries and rails to arrive, which is expected to arrive between the end of April and the start of June. The arrival of these materials is likely to affect our lead times down the line.

Purchasing for materials for Batch 7 has also started, which should put us around August-September when we’ll start Batch 7.

LaserBeam

Power supplies and heatsinks for the LaserBeam have arrived, and we are currently packing and assembling kits. Here’s one of our staff putting together the laser and heatsinks.

We’re expecting to start shipping the kits out at the end of the week this week or the start of next week. Ikenna is waiting on Bittele to wrap up the PCB assembly to finish up the drivers on Thursday. There were some delays due to chip and parts shortages for the assembly, but the boards have started fabrication last week. We’ll have around 400 new drivers arriving to wrap up the production for the rest of the LaserBeams.

Other general updates

Chris has made a lot of progress in the assembly instructions for the MK2 machines. Make sure to check it out in the resources. Thank you Aleks for being part of this project as well!

I also wanted to share some pics of the new power supply:

You can see that when you cut it open (I used an angle grinder), it is completely encapsulated. Although this is pretty overkill, this construction will basically make the power supply impervious to dust and moisture.

Did you see our April Fools video?

Ikenna initially suggested the idea of making a lasergun using the LaserBeam. I thought that it was a great idea so I put one together.

Assembly of the Not-a-LaserGun

The Not-a-LaserGun was partially inspired also by the Not-a-Flamethrower, which was a flamethrower created by Elon Musk.

Basically, the Not-a-LaserGun takes the LaserBeam diode assembly and driver assembly and replaces the power supply with a 12V 8A battery to allow the user to use the laser on battery power. Everything was then put into a case that was 3D printed in multiple parts. An Arduino was used to generate an on-signal when the trigger is fired.

The result of this was basically a super-powerful laser pointer that can burn stuff.

Extension Kits and MK2 48x30s

We now have three people with the extension kits. Dale, Garrett, and Dana. These guys also all have MK2 machines as well, so they will be able to compare the MK1 and MK2 as well. So far, the response has been very positive, with very few issues with the overall setup. There are a few kinks to work out however which include

  • Proper defaults and integration on gSender
  • Testing and finalizing designs for wire management
  • Instructions and other resources for assembly and use

We’ve asked our users and testers to start extending their MK1 machines since…well this is what I said:

We also just got in the aluminum part to adapt the new T12 nuts for the T8 spacing (used on the MK1 machines).

Please keep an eye out for further development updates and other feedback!

March 2022 Production Update Pt2. – Saga of delayed container MAGU5348230

Hey everyone, this is an update for this month’s production update, covering the status of some of the parts that we are waiting on to have come in as well as other details.

If you’re learning about the LongMill MK2 for the first time, please check out this post for more info.

Just as a reminder, if you’d like to get these updates as a weekly email newsletter, please subscribe here: https://sienci.us13.list-manage.com/subscribe/post?u=720f140325aaa668a8aa09916&id=e18d59a085

The TL;DR

We now have a definitive answer on when the power supplies we need to start shipping LaserBeams and LongMills again will be arriving to us. The container of parts and materials has been loaded onto the train this past weekend (March 19) and are expected to arrive in Brampton at the end of the week (March 25). Unloading to the warehouse can take between a few days up to two weeks. So we are conservatively estimating that the first units will start shipping at the start of April.

When will the LongMill MK2s start shipping? The saga of delayed container MAGU5348230

The last time we had a “saga” was back when we were scrambling to figure out the v-wheel situation. 2021 and 2022 shipping delays, especially for that last batch of parts have been another epic saga in itself.

Around June last year, we started Batch 5. Knowing the current world situation with COVID and everything, we started production on Batch 6 in the first quarter part of the production of Batch 5. This was the earliest we ever started sourcing parts for a batch, as we typically wait for the middle of the batch to start ordering parts. Batch 6 is also the largest batch we’ve ever created, as we wanted to hedge having part shortages by keeping more inventory on hand. With the majority of parts produced for Batch 6 being produced between August and December of last year, we expected to have a lot of buffer between each batch.

Well, then things went gangbusters from August to the start of this year, throwing our projection that we were going to run out of machines at the start of 2022 straight out the window. Instead, we ran out of LongMills sometime in December.

Given that we saw this upward trend happening, we had ordered as much stuff as we could early in advance. But there were a couple of minor issues. One of the biggest that is having repercussions now would be the chip shortage.

Due to the chip shortage, our regular suppliers for power supplies were 1) significantly increasing their prices 2) had an extremely long lead time that couldn’t deliver on schedule for our production. It was also uncertain if the power supplies could even be made, as the estimates we were getting relied on whether the chips would actually come back in stock again. With this going on, we started vetting and testing power supplies from other suppliers. For many producers, it was a similar story of very high prices and being unable to ship quickly due to the lack of chips.

Luckily we were able to work out the production for the power supplies with another manufacturer that was able to provide a high-quality product with the proper certifications and also have everything completed and ready to ship by December 1, 2021. Materials were picked up from the factory and prepped for transport on a cargo ship.

Although it was cutting it tight, we let customers know that we were expecting to start shipping LongMills in February to end of March, which would have given us just about 4 months to wait for the arrival of the power supplies. Back before the pandemic, ocean shipping speeds were fairly consistent and reliable, typically taking around 6 weeks for materials to arrive from China. Most delays, if any would generally be with loading and unloading, as sometimes things would get held up with customs or waiting for the next ship to arrive. During the pandemic, we saw shipping times shoot up to 8 weeks, and near the end of 2021, get to 12 weeks.

The estimated time that the power supplies and other parts would be arriving was January 30th initially, and we first set up our timelines based on this initial estimate. However, that has shifted due to delays in shipping. There were a couple things we believe caused these delays.

First was the aggregation of three other shipments that were getting sent here from China. We had two other shipments that were leaving from the same shipping company. We suspect that the shipper aggregated them together to save costs, rather than creating three separate shipments. Although when done properly, this does not affect the shipping time and usually is a win-win for both parties if the savings are passed onto us as well, combining shipments generally creates longer shipping times as each batch of cargo needs to wait on each other and can cause customs complications. Because of this, we never ask our shippers to combine cargo, and this was done without our consent.

Unfortunately, if we were to cancel the shipment, the time it would have taken to rebook shipments would offset any potential time savings for the shipment, so we had to go ahead with the current shipment.

Next was the trajectory of APL Vancouver, the cargo ship our stuff was on. Cargo ships can either make a straight trip from one port to another, and some will pick up and drop off cargo from multiple ports. In this case, it was the latter. Due to port congestion happening in many ports, this also added total transit time for our shipment. We weren’t aware of this until it was halfway across the ocean as well.

And lastly, general port congestion in Prince Rupert and on the rail system further delayed the shipment. According to Vanterm, the location that the container finally arrived at in Canada, there have been railcar shortages delaying containers from moving out of the rail terminal. Although our shipment arrived on Feb 13, 2022, it had been sitting waiting for rail cars to arrive for over 4 weeks.

So where does that leave us now? We now have confirmation that the shipment is now on rail and is expected to arrive on March 25th. Once the cargo arrives in Brampton, which is where the next railyard is, it will be unloaded and placed in a warehouse for pickup. Then we can arrange a truck to pick our shipment up and we’ll have everything ready to go for shipping.

Based on estimates from the shipping company, it takes roughly two days for unloading the train and two days for it to arrive at the warehouse. We are working on arrangements for a truck to go pick up the parts now so that it will be here the same day it is released.

So in regards to everything else, once we have those power supplies, we can start shipping. We have all of the other parts here to start shipping (minus some final packing materials), so we’ve been packing and prepping everything to go as soon as possible. As Kye (inventory manager) would say…

I’m glad that the saga is coming to an end. In hindsight, there could have been a couple of things we could have done and a few things we learned. One of them would have been to express ship a small batch from the original batch of parts to have them on hand as an emergency. Second would have been to get more visability on the status of the shipment. One of the problems was that on the system, it was showing that our stuff would be arriving on time, but that was because our operator was not updating the system. We needed to find info out about the shipments by calling or emailing directly. If we were aware of the delays earlier, we may have been able to react faster and make other arrangements.

Status of materials

Front and back feet

In our last update, we talked about parts that were expected to arrive on the week of March 7th. I’m happy to announce that these parts have now arrived and are being packed and assembled:

  • X, Y, Z gantries
  • Dust shoe brackets
  • Drag chain brackets
  • Dust shields
  • V-wheels
  • Cables
  • Assorted packaging
  • 3D printer filament
  • Inductive sensors

Here are the parts that we are still waiting on:

  • Power supplies (1-3 weeks)
  • Dust shoe boxes (this week)
  • Rail boxes (this week)

Production and assembly

We’ve been making good headway into production and assembly, and materials needed to ship the first batch of machines that we have on hand have now been pre-packed.

Future lead times

Once container MAGU5348230 arrives, we will have 1500 or more units worth of components for the LongMill MK2 12×30 and 30×30 with some exceptions. The two major parts that will be our next bottlenecks are likely to be the aluminum extrusion and the steel parts (gantries, drag chain mounts, feet). Both the rails and steel parts were made at 500 units worth, so we can make tweaks to these parts after the first batch.

Even with delays, sales have continued to be strong. We currently have around 400 units accounted for, and are expecting 500 units sold in the next couple of weeks.

Currently, another batch of rails is expected to ship in early June for another 500 units. We may be looking at extending lead times once we sell the first 500 LongMills as we may be waiting for the next batch of rails to arrive. Almag has been good at getting things shipped out on time or early so there is a chance we might get these parts earlier.

Steel parts are now starting production. We’ve given the go-ahead for some parts that don’t need changes, but we are expecting to finish the tweaks this week. Nithside, our manufacturer for the steel parts has told us that they are shooting to finish the batch this time within 3 weeks, as they were able to streamline some of their processes during the last batch. Total turnaround time with cutting, forming, and coating is expected to be around 6 weeks.

Once we are a bit further into the production, we’ll update our pages with new lead times.

LaserBeam

I talked with Ikenna about the status of the pending LaserBeam orders. We were able to ship some once we had more power cables arrive, but we are now waiting on copper heatsinks and power adapters to arrive to complete the production. The parts that we need for shipping are in container MAGU5348230, so we are facing the same delays as the power supplies for the LongMills.

We are currently producing and stockpiling parts and assemblies for the driver enclosure and shields, and we also have received another batch of laser goggles, fans, and lenses to cover for the next batch.

LongMill MK2 48×30 and Extension Kits

We’ve now received the:

  • T12 lead screws
  • 6001 Flange Bearings
  • T12 Delrin nuts
  • T12 ACME nuts
  • Longer drag chains

To get prepped for shipping, we still need to get:

  • Extension cables and wiring
  • Y gantry plates
  • MK1 to MK2 Delrin nut adapter

We just received our sample batch of extension cables. These will let our customers extend the length of the motor cables and inductive sensors. One they have been checked and tested, we’ll order a batch. We’ll also sell these on the store as extras so that customers can extend their cables if they need.

I’ve been using our 48×30 machine here and it’s been great! Currently, it’s just been used for general projects both large and small. Here’s a subwoofer box that I was working on for my car.

One thing I realized that was actually super handy about the 48in width was the fact that I didn’t need to cut any material down to fit the machine. All I did was put some half sheets of MDF that we had on hand, and just moved the mounting for the material down the middle, so I could just reposition the material to the area I wanted to cut.

I also put together a prototype machine for the MK1 to MK2 extension kits. At first I had a lot of issues with it, as it was getting stuck in travel, but it turned out that I had used a bad batch of prototype plates that had offset the bearing spacing by 3mm, causing the machine to bind. Replacing them has fixed the issue.

We are now starting to work with our beta testers to get the larger machines in their hands. The first two beta testers will receive their machines this week. Watch out for more news!

March 2022 Production Update

Hey everyone, here’s the latest production update. For previous updates, please read our blog.

Folks doing projects and testing in the workshop

Materials are arriving

We’ve received a large number of materials over the last couple of weeks including some of the steel parts, power and USB cables, packaging, dust shoe parts, end mills, and more. We’ve made good progress doing the packing and processing, with most of the materials we’ve gotten in prepared for shipping once we receive everything.

We’re also expecting 3D printing filament, gantries, control boards, and other steel parts, and v-wheels to arrive any day now, as transport has been booked and are awaiting delivery this week.

Waiting on materials to arrive

We continue to wait on the shipment of power supplies for the LongMill and LaserBeam and other parts that arrived on Feb 13 at Prince Rupert. Due to rail congestions, we are still waiting on these parts to arrive. According to our updated tracking info, it is expected to arrive in the next two weeks. However, due to the uncertainty with when these parts will be moved onto rail, as well as potential transit time for truck freight from the Mississauga warehouse, we would advise customers that this shipment may not reach our shop until the end of the month.

We are frustrated with the delays in these shipments, as this shipment was expected to arrive at the end of January. We are hoping that these items will arrive soon, and in the meantime, we are doing our best to pre-pack as much as we can so that we can ship machines out as quickly as we can when they do.

By the end of this week, we are expecting to have all of the materials ready to ship the MK2s with the exception of the power supplies, which will be our biggest bottleneck.

Given these delays, for new orders placed today and onwards, customers should expect to receive their machines in April/May.

Packing progress

Rails ready to ship

We’ve been processing materials as they come in. Most of the day-to-day packing isn’t super interesting but we did make a small modification to the printers in our print farm that some folks might find interesting. With the new MK2 dust shoes, the height of the hose comes out to be around 196mm. Unfortunately, the printing height of the Prusa Minis we have in the farm, which make up the majority of the printers we have, only print up to 185mm. Initially, we printed the hoses on some of the other printers we have in the farm, we weren’t able to keep up with the number of hoses we needed to print. So, we had the brilliant idea to just make the Prusa Minis a little bit taller. After making a small simple spacer, we’re now able to print the dust shoe hoses on the Prusa Minis!

Now with 6 of our printers converted, we can now print up to 18 dust shoe hoses per day, meaning that we should be caught up with the printing in the next two to three weeks.

We’re also excited to get our 3KG filament spools to replace the 1KG spools, which means that we’ll be able to reduce the number of filament changeovers by 2/3rds, improving our printing efficiency and the amount of manpower it takes to run the farm.

Assembling dust shoe hoses

Dimensioned drawings are now updated for all LongMill MK2s.

We’ve now updated the dimensioned drawings for all of the LongMill MK2s to include the 48×30 as well as overall width and heights of the machine so that customers can prep their work areas, enclosures, and tables.

Wrapping up the instruction manual

Chris and Aleks have been hard at work making the new instruction manual and working with our staff and beta testers to perfect the assembly manual. We’re excited to share a final draft of the MK2 assembly instructions. Please note that there are still some minor updates that we need to make to finalize the manual, including making a compressed version (right now the PDF is 107MB large) and updating links for the add-ons, but we just wanted to share this with everyone to get thoughts and feedback, as well as people can get an idea on what the assembly process for the MK2s are going to look like.

LaserBeam production

New batches of drivers and other components are currently in production. We are experiencing delays with driver manufacturing as we need to adapt to component and chip shortages. Based on these supply chain issues, customers are advised to expect delays when ordering the LaserBeam. We are also waiting on power supplies and copper heatsink housing parts to arrive with the large shipment delayed in Prince Rupert to arrive to complete currently pending orders.

While we wait on parts to arrive, we’ve completed the wiring and have been assembling other parts, such as the air assist and driver housing components to prepare for the arrival of the parts.

We have pushed orders that were scheduled to ship end of Feburary to end of March, and we are advising a 8 week lead time for new orders.